Hanover Quay Mixed Commercial Development

The project consisted of 68 Apartments and 5700m² of office space with 4 large retail units at the bottom facing the water.

Development Summary

The project consisted of 68 Apartments and 5700m² of office space with 4 large retail units at the bottom facing the water. The project was built on the footprint of the old Gas works yard and resulted in 50,000 tonnes of contaminated soil being shipped to Germany for treatment from the excavation of the basement.

This involved a complicated waterproofing exercise to avoid the existing contaminated water on site getting into the canal adjacent to the building. The project also consisted of a full landscaped courtyard and individual roof gardens on each building to highlight its location.

Key Facts
Client Ellier Developments Ltd.
Sector Residential
Area 13,247sq.m.
Architect Burke Kennedy Doyle
Quantity Surveyor Davis Langdon PKS
Duration 24 months
Value €40 Million