The project involved the fit out of approx 25,000 sq. ft. high specification Irish Head Office for solicitors Maples and Calder.
The project involved the fit out of approx 25,000 sq. ft. high specification Irish Head Office for solicitors Maples and Calder. The Bennett Construction team worked very closely with the client to ensure the design facilitated a fast track programme.
This extensive fit out was completed in 11 weeks, thus allowing the client to relocate from their existing premises saving them considerable money by not having to extend their existing lease. The project was phased to facilitate the early relocation from the clients existing premises with the first floor being handed over in 8 weeks.
The fit-out included the construction of a considerable extent of cellular offices, consultation rooms, board room, high specification reception and dining room including floor, wall, ceiling finishes, partitions and joinery, mechanical, electrical services and kitchen installations.