NEC Semiconductors Ireland Ltd

The project involved the construction of a new steel framed production plant and ancillary buildings with additional high specification office accommodation

Development Summary

The project involved the construction of a new steel framed production plant and ancillary buildings with additional high specification office accommodation. Contained within the new plant were a series of category one clean rooms with associated gowning and service areas. In addition to the main buildings, Bennett also constructed ancillary workshops, plant services buildings, and a new sub-station.

Extensive roadworks and landscaping (which included a pedestrian bridge over an adjacent river) were also carried out. All work had to be carried out without any disruption to the existing production activities; which necessitated close co-ordination with the Client throughout. The new plant was ultimately joined to the existing plant over a series of week-end and holiday periods and also involved night time handovers of areas to suit the Client requirements.

Key Facts
Client NEC Semiconductors Ireland
Sector Industrial
Area 60,000 sq.ft.
Architect Keane Murphy Duff
Quantity Surveyor KMCS
Duration 14 Months
Value €14 Million