Gilbeys Office & Distribution Facility

The project involved the construction of a new dry goods warehouse on a green field site

Development Summary

The project involved the construction of a new dry goods warehouse on a green field site, together with a two storey office block, plant services building and a security building. The contract also included the construction of a vehicle marshalling area and a car park. The project was fast tracked, with detailed design taking place as the works progressed on site, with Bennett personnel providing ‘buildability’ solutions to the design team as required.

Key Facts
Client Gilbeys Ireland
Sector Design and Build
Area 70,000 sq. ft.
Architect Brian O’Halloran & Associates
Quantity Surveyor Keogh McConnell
Duration 35 Weeks
Value €10 Million
web development by One Productions