Successful Handover of Barrow Street Link Bridge

Date added: 30 Jun 2014

Bennett Construction have successfully handed over the Link Bridge on site at Barrow Street in Dublin.  The Link Bridge project was a Design and Build contract with GIG as the main contractor.   It is a pedestrian bridge that is 8 meters over Barrow Street and run from the our Clients Main Docks building to thier Gasworks building and Gordon House at their 2nd floor level.  

GIG GmbH were responsible for the design and installation of the steel structure and glazing.  

Bennett are in control of the site set up, logistics, refurbishment works to the 3 client buildings, internal finishes to the bridge and the Mechanical, Electrical and Sprinkler works.  The programme was 41 weeks for design and build.